We're glad you stopped by to learn more about the Campus Life Center. Keep up with the updates here or by following #CLCupdate on Twitter.

Week of August 14, 2017

Week of August 14, 2017

This Week: Happy Move In!

The start of school is nearly upon us and we are anxious to welcome students back on campus! No construction work will be taking place during move-in weekend (this Saturday-Sunday, August 19-20).

During the first part of the week, we will continue demo on remaining concrete structures, hauling off debris to the recycling center, and working on the new water line to the CLC.

Question of the Week

When will the plywood on the AMUC be removed?
The plywood covering the AMUC is meant to protect the historical facade during the early stages of construction, when there is a risk of equipment or materials damaging it.  Once the early stages of construction are complete, the plywood will be removed, likely late in the fall semester or early in the spring semester.

Next Week:

Late next week, a section of the concrete pad at the loading dock of the AMUC will be removed in support of the new steam service that will connect the AMUC to the campus steam distribution system. 

 

Week of August 21, 2017

Week of August 21, 2017