2014

October: CLC concept designs submitted by potential architects.

November: Jury review of semi-finalists. Finalists announced.


2015

January: Dialogue sessions with finalists.

March: Final design submissions due. Finalist designs displayed for public comment. 

April: Jury review. Architect announced.

October: Complete programming phase.


2016

February: Complete schematic design.

September: Complete design development.

October: Begin construction of DUC-ling dining center.


2017

April: Complete construction documents. Finish construction of DUC-ling dining center.

May: Move out of DUC west wing. Dining move into DUC-ling. Demolition of DUC west wing begins.


2019

May: Opening of new Campus Life Center